Logicool were approached to provide a quick turnaround solution to provide equipment for a critical testing lab. The site was ready to go with concerns about the existing Air Conditioning solution as the site is a critical medical test facility. Logicool proposed a Mitsubishi Electric Design and Build solution to match the exact requirements of the facility including technical challenges as well as on-site services.
Five Mitsubishi Electric Mr. Split Systems
Ten Mitsubishi Electric Y Series Heat Pump Systems
Six Mitsubishi Electric R2 Series Heat Recovery Systems
Mitsubishi Electric AE-200 Central Controller
Sixteen Mitsubishi Electric Mr. Slim AHU Interface solutions service Five Air Handling Units
Modbus and BACNet Interfaces
Design Assistance
Commissioning Assistance
Support to BMS Partner enabling integration of Modbus and BACNet
Management of logistics challenges to enable plant delivered in time for six-week installation window