Chiller Installation at Manufacturing Plant, Derby

Site Location

Derby

 

Scope

Logicool were approached to provide a fast turnaround solution to provide a replacement chiller for a large office facility based at a manufacturing facility in Derbyshire. The project had previously been designed and quoted a number of times but due to the Capital cost of the equipment and budget constraints, the project was only given the green light in Spring 2024 with a required supply, installation and commissioning turnaround of only six weeks. 

Logicool were able to react quickly and reselect the equipment to ensure that the cooling and heating loads were met, the project was within budget and the contractor could meet the tight deadlines required. Other manufacturers were only able to provide lead times of, at best, 16 weeks. Logicool were able to select and deliver this equipment within one week. 

Mitsubishi Electric E-Series Chillers were selected for this project. 

Equipment

Four Mitsubishi Electric e-Series Chillers

BMS Interfaces

Services

Design Assistance

Commissioning Assistance

Support to BMS Partner enabling integration of Modbus and BACNet

Management of logistics challenges to enable supply of equipment in short timeframe.